Design build construction of 45,000 SF soldier pile, lagging and tieback wall for future UofO Basketball Arena.  Soldier piles installed using the CFA method, greatly increasing production in soft, saturated silts and clays.  Included 280 soldier piles and 255 tiebacks with a 35-day baseline schedule.